Protected Membrane (Inverted) Roofs and Paver Terraces: What Owners Should Know
Published November 8, 2026
What is a protected membrane roof?
A protected membrane roof, or PMR, turns the usual roof build-up upside down. The waterproofing goes on the deck. The insulation goes over it, usually with filter fabric and ballast or pavers above that. You will also see it called an inverted roof membrane assembly, or IRMA.
DuPont’s installation guide for its extruded polystyrene system, a Canadian edition that explains the principles, says this setup keeps the membrane at a nearly constant temperature and protects it from weathering and foot traffic. That is the insulation manufacturer’s claim.
For an owner, the main difference is practical. In a conventional roof, the membrane sits on top and takes the sun, ice, and foot traffic. In a PMR, the membrane is buried under the insulation, so water runs above the membrane, loads sit on the insulation, and any repair starts with taking up the layers above.
Where does a paver terrace fit?
On this kind of roof, the pavers are the walking surface. They sit over the insulation, and the manufacturers put clear conditions on that assembly.
Johns Manville’s modified bitumen specifications say pavers used as ballast must be placed on supports or pedestals, for example 6-inch squares of its DynaTred Plus that give a minimum half-inch air space so moisture vapor can vent. JM also states, in capital letters, that roof areas where pavers are in direct contact with the insulation are excluded from a JM Peak Advantage Guarantee, including its thermal overlay portion. That is the manufacturer’s term, and our warranty guide explains how exclusions like this work.
DuPont gives the reason for the air space. If the insulation is trapped between an impermeable surface like pavers and the deck, vapor cannot escape and gets driven back into the insulation. Its guide also says wearing surfaces in direct contact can trap moisture so repeated thaw cycles spall their undersides.
DuPont recommends concrete pavers of at least 3,000 psi concrete weighing at least 18 lb/ft2 on pedestals. The federal specification UFGS 07 55 00 calls for air-entrained concrete pavers at least 1-1/2 inches thick and 3,000 psi. Those are product specs. Your design professional still has to set the paver and weight for your roof.
How does drainage work on a protected membrane roof?
Drainage makes or breaks this kind of roof.
JM says positive drainage must exist and recommends at least one quarter inch per foot on the finished membrane, because even insulation with drainage channels retards water against the membrane. JM also treats areas where water ponds more than 24 hours as unacceptable and ineligible for its guarantee.
UFGS 07 55 00 comes at the same issue from the other side. It says drainage is critical because the insulation will float if submerged and not adequately ballasted. It also says pavers over hidden drains must be marked so drains can be inspected.
New York City adds code on top of that. BC 1511.1.1 requires every reroof to provide positive drainage. An inverted roof still needs secondary drainage where the perimeter would trap water. See our drains and ponding guide.
Then there is the weight. Pavers, pedestals, and insulation add dead load, and BC 1511.2 requires the roof structure to carry the covering system and the loads of installation. The design professional must confirm the deck can carry the full overburden.
Why test the membrane before covering it?
Because once the insulation and pavers are down, the membrane is buried.
UFGS 07 55 00 requires that after the membrane and flashings are installed and before insulation is placed, the drains are plugged and the roof is flooded for 24 hours, with leaks remedied before insulation is placed. Skip that, and a leak repair starts with taking up pavers and insulation.
The fire sequence matters too. JM warns that extruded polystyrene insulation is combustible and should never be exposed to an open flame or other ignition source. On a roof that uses torch-applied flashings, that points to sequencing, with flame work finished and cleared before polystyrene goes down. FDNY’s rules on torch fire watch are summarized in our modified bitumen guide.
What does the NYC Building Code say about terraces?
BC 1504.9 sets cool-roof reflectance rules for roofs with a slope of 2:12 or less: initial solar reflectance of 0.7 with emittance of 0.75, or an SRI of 82. For terraces, these exceptions matter:
- Terraces on setbacks comprising less than 25 percent of the area of the largest floor plate (exception 1).
- Any portion covered by a green roof system complying with BC 1507.16 (exception 2).
- Roof used as outdoor recreation space that is landscaped, decked or covered with a walking surface, if that surface has an initial solar reflectance of at least 0.3 (exception 3).
- Ballasted roofs where the ballast has an initial solar reflectance of at least 0.2 (exception 4).
- Any roof where the area not covered by exceptions 1 through 7 totals less than 100 square feet (exception 8).
BC 1504.8 also says aggregate, gravel or crushed stone shall not be used as surfacing for roof coverings, and the BC 1508.2 table lists extruded polystyrene under ASTM C578. JM and DuPont both publish gravel ballast options, so do not rely on a generic manufacturer detail without asking the designer how that gravel option works with BC 1504.8 and the local reflectance rule.
Green roofs sit under a separate section, BC 1507.16. That section requires ANSI/SPRI RP-14 and VF-1 or FM DS 1-35, with exceptions for small or low roofs and container gardens.
Which membranes go under a protected assembly?
There are several published options.
JM states its APP and SBS modified bitumen specifications are eligible for protected membrane assemblies. Kemper says its AC Speed FR PMMA membrane suits inverted roofs because it needs no seams or termination bars and can be covered with tile, paver, pavement or growing media.
Soprema’s ALSAN RS brochure lists overburden systems for garden roofs, IRMA, pavers and water features. WestWood’s system guide shows pedestal paver and vegetative overburden over its PMMA with FLL-certified root resistance for green roofs. Details of those products are in our PMMA explainer.
What matters on your job is simple. Check the data sheet for the exact product and the overburden it is approved to carry.
What does Altius CM do on paver roofs?
At 401 East 65th Street the roof received a liquid-applied membrane and Hanover porcelain pavers throughout. The case study explains the scope.
At 311 Franklin Avenue the team designed and built the tapered insulation, installed a 2-ply roofing system and finished 2,000 sq ft of roofing and pavers.
The project records do not state whether either roof is a protected membrane assembly, so we do not claim it. Related services: plaza reconstruction and roof and facade waterproofing.
Altius CM installs systems from Johns Manville, Siplast, Holcim Elevate, Soprema, Kemper System, ALT Global (WestWood USA) and Olmeck. This page quotes the published documents of DuPont, Johns Manville, Kemper, Soprema and WestWood; none of them has certified or endorsed Altius CM.
What should an owner check before approving a paver terrace?
- The membrane type, the overburden it is approved for, and the manufacturer’s guarantee terms.
- Slope and drain access, including marked drains under pavers.
- A flood test before insulation, with documentation.
- Paver support, air space, weight, and the structural check for dead load.
- Reflectance compliance under BC 1504.9, including which exception is used.
- A plan for future repair: who lifts what, and how the layers go back.
Sources
- DuPont, Protected Membrane Roof Installation Guidelines (Canada edition)
- JM APP Modified Bitumen Specifications, section 16
- JM SBS Modified Bitumen Specifications, section 27
- UFGS 07 55 00, Protected Membrane Roofing (Aug. 2025)
- Kemperol AC Speed FR, Kemper System
- Soprema ALSAN RS brochure
- WestWood USA system reference guide
- 2022 NYC Building Code, Chapter 15
Last verified: November 8, 2026. This is general information, not legal advice or an engineering opinion; have a registered design professional confirm slope, loads and reflectance compliance for your roof.
Frequently asked questions
What is a protected membrane roof?
A roof in which the insulation sits on top of the waterproofing membrane instead of under it, usually with a filter fabric and ballast or pavers above. It is also called an inverted roof membrane assembly (IRMA). The DuPont installation guide for the system says this sequence protects the membrane from extreme temperature change, weathering and foot traffic, a claim made by the insulation manufacturer.
Do pavers on a roof need pedestals?
Manufacturers say so. Johns Manville states that when pavers are used as ballast over a protected membrane assembly they must be placed on supports or pedestals, such as 6-inch squares of its DynaTred Plus that give a minimum half-inch air space, and that areas where pavers sit in direct contact with the insulation are excluded from coverage under its Peak Advantage Guarantee. DuPont recommends pedestals or a ventilating air space so the assembly stays vapor-open.
What drainage does a protected membrane roof need?
Poorly drained ones are a problem. Johns Manville says drainage must be positive, recommends a minimum slope of one quarter inch per foot on the finished membrane because insulation and its channels retard water flow, and treats areas where water ponds more than 24 hours as unacceptable and ineligible for its guarantee. The federal guide specification UFGS 07 55 00 warns the insulation will float if submerged and not adequately ballasted.
Does the NYC Building Code exempt paver terraces from the cool roof rule?
Partly. BC 1504.9 exempts a roof area used as outdoor recreation space that is landscaped, decked or covered with a walking surface, if that surface has a minimum initial solar reflectance of 0.3, and exempts ballasted roofs whose ballast has a minimum initial solar reflectance of 0.2. Terraces on setbacks smaller than 25 percent of the largest floor plate, and green roof areas, are also exempt.
Should a protected membrane roof be leak-tested before the insulation goes on?
The federal guide specification UFGS 07 55 00 requires it: after the membrane and flashings are installed and before insulation is placed, plug the drains and flood the roof for 24 hours, then fix any leaks before insulating. Once pavers and insulation are down, finding a leak means lifting them.
Can a liquid-applied membrane be used under pavers and insulation?
Manufacturers say yes for their products. Kemper says its Kemperol AC Speed FR membrane is ideal for inverted roofs because it has no seams or termination bars, Soprema lists ALSAN RS overburden systems for garden roofs, IRMA and pavers, and WestWood lists exposed, buried and inverted assemblies. Check the data sheet for the specific product and the overburden it is approved to carry.