From Inspection to Repair: An Owner's FISP Timeline, Step by Step
Published November 8, 2026
What happens between a FISP inspection and a completed repair?
There are four clocks to watch under 1 RCNY 103-04.
The report has to be filed within 60 days of the inspector’s final inspection. Unsafe conditions have to be corrected within 90 days of submission. Repairs and the amended report should be wrapped up within 104 days, or an extension is needed. Once repairs are finished, the amended report is due within two weeks.
The QEWI handles the filings. The owner is still on the hook for the deadlines and hires the repair contractor.
Use Day 0 as the day the report is submitted to DOB.
| When | What happens | Who |
|---|---|---|
| Before inspection | Review prior reports, design inspection program | QEWI |
| During inspection | Notify DOB and owner immediately of any unsafe condition | QEWI |
| Up to 60 days after final inspection | Report filed | QEWI |
| Day 0 | Report submitted, public protection and repairs start | Owner |
| Day 90 | Unsafe conditions must be corrected | Owner |
| Day 104 | Repairs done and amended report filed, or extension requested | Owner, QEWI |
| Within 2 weeks of repair completion | Inspection and amended report | QEWI |
What happens before the report: inspection and notification
The QEWI starts by reviewing the most recent report and any available earlier ones. Then the QEWI sets the inspection program for your building.
Your part is access. Close-up inspections are required at intervals of no more than 60 feet along paths from grade to the top of each wall facing a public right-of-way. See access methods compared.
If the QEWI finds an unsafe condition, DOB and the owner have to be notified immediately. That notice has to include the location, advice on protective measures, and the recommended type and location of public protection. It does not wait for the full report. Immediate hazards, such as loose masonry, are the kind of situation covered in emergency structural repair.
When is the report filed?
The report is due within 60 days of the final inspection date. If that deadline is missed, a new critical examination is required.
If DOB rejects the report, a revised one is due in 45 days.
The filing also has to fall within the building’s filing window. That is covered in Cycle 10 filing windows.
What must the owner do on day 0 of an Unsafe filing?
Once an Unsafe report is filed, the owner, agent, or person in charge has to immediately start repairs and any protective measures needed to secure the public. That can include sidewalk sheds, fences, and safety netting. DOB notes that those protective measures require DOB permits.
This is when the repair scope turns into actual work. The report has to list the permits the repairs will need. The owner hires a repair contractor, and the contractor prices the work, schedules it, and arranges access.
Our guide to repair methods explains common facade scopes, and facade repair and replacement describes the work. Altius CM works nationally, including across NYC, as the repair contractor. It performs the repairs the owner contracts for and coordinates access and sequencing with the owner’s QEWI, who inspects and files.
For shed permits and the newer repair milestones tied to them, see our Local Law 48 shed guide and Local Law 51 milestones.
What if 90 days is not enough?
If the scope is too large for 90 days, the QEWI has to recommend a longer time frame in the report. The rule does not allow time frames over five years.
The owner has to finish the work within that time frame and notify DOB of any deviation.
The extension path is separate. The Commissioner may grant up to 90 days on the QEWI’s application. That application needs notice that the premises are secured, the repair contract, the inspector’s time estimate, the permit statement, a notarized owner affidavit, and the fee.
A further extension is considered only for unforeseen delay affecting substantially completed work, unforeseen circumstances such as fire or building collapse, a hazard that takes more than 90 days to remedy such as a new wall, or progress photos of current repairs.
For both paths, the rule states that financial considerations are not accepted as a reason.
What happens when repairs finish?
Within two weeks after repairs are completed, the QEWI has to inspect and promptly file an amended report with the fee. The owner has to obtain permit sign-offs as appropriate.
If DOB rejects the amended report, a revision is due in 45 days.
The QEWI has to inspect finished work, so access has to be ready. Open permits also have to be signed off. Sheds stay in place until DOB accepts the amended report, unless the QEWI gets permission to remove them on a signed and sealed statement.
What if the rating was SWARMP?
A SWARMP condition does not run on the 90-day clock.
The inspector’s report gives a date, at least a year out, by which the work has to be performed. The owner can complete the work earlier, and a subsequent report can update the status within the cycle.
At the next inspection, the QEWI certifies each prior repair or reports uncorrected conditions Unsafe, with a $2,000 penalty. See FISP ratings explained.
What does a missed step cost?
For Unsafe conditions not corrected, the penalty is $1,000 per month, plus $10, $20, $30 and $40 per linear foot of shed per month in years 2 to 5. It continues until DOB receives an acceptable amended report showing conditions corrected, the shed removed and permits signed off, or an extension is granted.
Late filing is $1,000 per month. Failure to file is $5,000 per year.
A real project shows the repair side. At 529 West 42nd Street, a $3M+ FISP 9 restoration in progress, the scope covers floors 1 through 6 and grew as conditions were found once the facade was opened. 45 Crosby Street was a multi-phase facade and roof deck restoration with a similar pattern. See budgeting a facade restoration for planning contingency, and construction management.
Sources
Last verified: November 8, 2026. Individual filing history can change deadlines; confirm in DOB NOW: Safety and with your QEWI. This is general information, not legal advice.
Frequently asked questions
What is the total time from filing an Unsafe report to a closed-out filing?
The rule gives 90 days from submission to correct unsafe conditions and two weeks after repairs for the amended report. DOB's page says that if repairs cannot be completed and the amended report cannot be filed within 104 days of the original filing, the owner must request an extension.
Who files the extension request?
The QEWI submits the application. Under 1 RCNY 103-04 it must include notice that the premises are secured, a copy of the repair contract, the inspector's time estimate, a statement of permit requirements, a notarized owner affidavit that work will finish in the estimated time, and a fee. DOB's fee page lists $305 for an extension.
Can I take the shed down as soon as the repairs finish?
Not on your own. Sheds and other protective measures stay until DOB accepts the amended report. The QEWI may ask permission to remove the shed sooner with a signed and sealed statement that the conditions were corrected and the shed is no longer required, and DOB grants that at its sole discretion.
What does the repair contractor do in this process?
The contractor performs the repairs the owner contracts for and coordinates access and sequencing with the owner's QEWI. The QEWI inspects, classifies, files the reports and certifies completion. A contractor does not file FISP reports or sign off.
What if a SWARMP date will not be met?
The owner is responsible for notifying DOB of any deviation from the inspector's time frame. A subsequent report with supporting documents from the QEWI justifying a new time frame is required. An uncorrected SWARMP condition must otherwise be reported Unsafe at the next inspection.